1. The installation of insulation and screeds on the individual roof terraces has been completed, and the waterproofing has been completed.
  2. The work on the device of masonry of the internal walls of the 4th, 7th, 8th floors was completed.
  3. The installation of 1,500 m2 of window blocks was completed.
  4. Piles of the retaining wall of the entrance to the parking.
  5. Facade finishing work is being carried out. 4000 brackets were installed and 400 m2 of insulation were mounted.
  6. Excavation of the pit for Parking was completed and work began on the installation of a monolithic slab of passage and parking.