1. The work on the brickwork of the external and internal walls of the 24th floor was completed.
  2. The work on the device of masonry of the internal walls of 9, 10 floors was completed.
  3. Installation of 800 m2 of window blocks was completed.
  4. The masonry on the roof is completed.
  5. 12 facade cradles were mounted and work on the device for finishing the facades begins.