- The work on the device of masonry of walls at the level of -2 floors was completed
- The installation of metal-plastic windows has been completed and the installation of aluminum windows of penthouses at the level of 24-25 floors has begun
- Finishing work is carried out on the facades. 7500 brackets were installed and 1700 m2 of insulation were mounted.
- Completed vertical parking elements -1 level.
- Work has been done on the device of the parking slab 1 level.
- Carrying out work on the installation of piles and concrete preparation of entry into the parking lot from the side of ul. Pimonenko.
- Work has been done on the device of storm sewage from the roof of the house to level -2.
- Work is underway on the installation of vertical risers for water supply, heating and rainwater systems at the level of 5-11 floors.
- Work is underway on the installation of risers for household sewage in apartments from the 2nd to 9th floors.
- Work is underway on the installation of horizontal wiring of the heating system in apartments at the level of 19-22th floor.
More construction photos in our Gallery