1. The waterproofing works  on the individual roof terraces has been completed.
  2. The installation of insulation and screeds on the public roof terraces has been completed, and the waterproofing has been completed.
  3. The work on the device of masonry of the internal walls of the 2nd, 3rd floors was completed.
  4. The installation of 1,600 m2 of window blocks was completed.
  5. Piles of the retaining wall of the entrance to the parking.
  6. Facade finishing work is being carried out. 5000 brackets were installed and 600 m2 of insulation were mounted.
  7. The installation of a monolithic slab of Parking was completed.