1. The waterproofing works on the public roof terraces has been completed.
2. The work on the device of masonry of the internal walls of the 1st, -1 floors was completed
3. The installation of 1800 m2 of window blocks was completed.
4. Finishing work is carried out on the facades. 5000 brackets were installed and 600 m2 of insulation were mounted.
5. Completed vertical parking elements -2 level.
6. Work has been done on the device of the parking slab -1 level.
7. The waterproofing and backfilling works of parking’s walls has been completed
8. Work is underway on the installation of vertical risers for water supply, heating and rainwater drainage systems at the level of 2-4 floors.