1. The installation of gas boiler boilers has begun;
  2. The installation of screed apartments and corridors from the 15th to the 24th floor is being done;
  3. The arrangement of pipelines of the heating system to the gas boiler is being done;
  4. Finishing working on the facades. Installation of insulation brackets and tiles is being done;
  5. Installation of aluminum bay windows for apartments is being carried out;
  6. The horizontal wiring of the heating system, water supply at the level of 6-25 floors are being done;
  7. The installation of power supply systems and low-voltage networks of 9-25 floors is being done;
  8. The installation of the road furniture from Pimonenko St is being done.;
  9. Installation of air ducts for ventilation and smoke exhaust systems on the 1-25th floor is being carried out;
  10. Installation of fire fighting systems is being carried out.