- The installation of insulation and screeds on the individual roof terraces has been completed, and the waterproofing has been completed.
- The work on the device of masonry of the internal walls of the 4th, 7th, 8th floors was completed.
- The installation of 1,500 m2 of window blocks was completed.
- Piles of the retaining wall of the entrance to the parking.
- Facade finishing work is being carried out. 4000 brackets were installed and 400 m2 of insulation were mounted.
- Excavation of the pit for Parking was completed and work began on the installation of a monolithic slab of passage and parking.